commercialbatterystorageinstallation

EV Charging Hub Storage Install

Fleet depots, forecourts and destination charging on constrained connections. Sized from your half-hourly data, engineered around your switchgear, siting and fire strategy.

  • MCS
  • NICEIC
  • G99 / G100
  • PAS 63100

EV-charging storage is often the cheapest way to add chargers, because the alternative is a costly DNO reinforcement and a long queue. Rapid and ultra-rapid chargers create short, severe demand spikes; a battery charges off-peak and from any on-site solar, then discharges into those spikes, so the connection sees a smoothed load rather than the raw charger peak.

The install is a combined-system design: the battery, its protection and the chargers share the LV or HV infrastructure and metering, and a G100 limitation scheme holds the whole site within its agreed import and export capacity. We design storage and charging together so the commissioning proves the combined behaviour, not just the battery in isolation.

How we install ev charging hub storage install

Delivery runs: model the charging demand profile against the existing connection; design the shared LV/HV distribution, protection and metering; install the battery and charging infrastructure together; commission the G100 limitation and the buffered charging behaviour under load; witnessed testing across storage and chargers.

What this install includes

Typical ev charging hub storage install

Power / capacity
100 kW / 200 kWh-1 MW / 2 MWh
Project value
£120,000-£1.4m
Payback
7 years

Budget and capital allowances

Budget £120,000-£1.4m for this install, with a 7-year simple payback. On tax, a ev charging hub storage install qualifies for 100% AIA on the first £1m and a 50% first-year allowance on the balance (special-rate — not full expensing); we model capital, finance and lease routes side by side. See the cost guide, capital allowances and grants and funding.

Siting, fire and compliance

Fire separation between the battery enclosure and the charging bays is engineered per insurer and NFCC guidance, to PAS 63100:2024 principles and BS EN 62619 / BS EN 62933, with the charger installation to BS 7671 and OZEV requirements where grant-funded.

G99/G100 for storage and the combined site; charger installation to BS 7671 and OZEV scheme requirements where grant-funded. Fire separation between battery enclosure and charging bays per insurer and NFCC guidance. Coordinated commissioning of storage and chargers.

Getting it connected and signed off

Delivering a ev charging hub storage install means owning the G99 process end to end — application, protection settings, DNO liaison and G100 limitation on constrained networks — with the metering engineered for accurate control and settlement. Every install ends with a documented, witnessed commissioning and an O&M handover pack. Read our honest view on whether it is worth it.

EV Charging Hub Storage Install: at a glance

AttributeTypical for this install
Power / capacity100 kW / 200 kWh-1 MW / 2 MWh
Sitingn/a
Project value£120,000-£1.4m
Simple payback7 years
ConnectionG99 (G100 limitation where constrained)

Get a free ev charging hub storage install feasibility

Responds within one working day

  • 1. Free desk feasibility from your meter data and roof, no obligation.
  • 2. Site survey and a fixed-price proposal, itemised in writing.
  • 3. Install and aftercare by MCS-certified engineers.
  • MCS Certified
  • NICEIC
  • RECC
  • TrustMark

By submitting you agree to our privacy policy. We never sell your details.

Common questions

How long do the batteries last once installed?

Quality LFP commercial cells are typically warranted for around 6,000-10,000 cycles or 10 years to roughly 70% retained capacity, with real-world life often longer. We size with end-of-life capacity in mind so the system still meets its target late in life, and plan augmentation (adding cells) where it makes sense. The warranted cycle count and degradation curve are stated in every proposal.

Can you install storage to support new EV charging?

Yes, and it is often the cheapest way to add chargers. Rapid and ultra-rapid chargers create short, severe demand spikes that can trigger an expensive grid upgrade. A battery buffers those spikes, charging off-peak and from any on-site solar, so more chargers fit on your existing connection. We design the storage, protection, and charging infrastructure together and hold the combined site within its agreed capacity with a G100 scheme.

How long does a commercial battery storage installation take?

Physical installation is typically 1-6 weeks on site for a behind-the-meter system. The overall programme, however, is set by the DNO: a G99 study and connection can run 3-18 months depending on network capacity in your area. We submit the G99 application alongside the survey so the clock starts immediately, and use a G100 limitation scheme where it lets the project proceed sooner. Grid-scale standalone projects run 18 months to several years including planning.

What is the G99 process and why does it drive the timeline?

G99 is the Energy Networks Association connection agreement required for storage above 16 A per phase, which covers almost every commercial system. The DNO reviews the connection, may require a network study, and sets the protection and metering requirements. Because network capacity is limited in many areas, the study and connection offer are usually the longest item on the programme. We prepare the application, single-line diagrams, and protection proposals, liaise with the DNO, and, where the network is constrained, engineer a G100 export/import limitation scheme so the site can connect within its existing agreed capacity.

Containerised outdoor BESS or an indoor cabinet, which suits my site?

It comes down to space, capacity, and fire strategy. A containerised outdoor system is usually the fastest route to multi-MWh capacity and keeps the fire and space constraints outside the building, but it needs prepared hardstanding, separation distances, and firefighting access. An indoor cabinet suits smaller systems (roughly 60-500 kWh) at sites with a suitable plant room or switchroom, but the room must be compartmented, ventilated, and fire-detected. We assess both against your available space, target capacity, and insurer requirements at the survey.

Other install types

Accredited and certified for UK commercial work

  • MCS Certified
  • NICEIC Approved
  • RECC Member
  • TrustMark Licensed
  • IWA Insurance-Backed
  • ISO 9001 / 14001

Commercial Solar Across the UK

Weighing the numbers? See the business case for storage.

Check battery storage grants & funding.

Visit the UK hub for commercial solar installation.

Adding PV too? We also cover warehouse rooftop solar.

For generation on site, see solar for manufacturing plants.

Buffering chargers? Pair storage with workplace EV charging.

Get a free quote
Get a free quote