Commercial battery size pre-check
Three sums to sense-check a proposal for commercial battery storage installation before you ask for quotes. Arithmetic only: no prices, savings or payback, and not a design.
What the sums say
- Duration at full power
- 2 hours
- Minimum energy for the peak
- 400 kWh
- Grid route for this power
- G99 Type A
What to gather before you ask for quotes
- Twelve months of half-hourly meter data. It is the one input every sizing and savings case depends on. Half-hourly metering is also what the network operator expects where export is metered.
- Your supply capacity and the site's real peak, from the data rather than from memory.
- What the battery is for: covering peaks, shifting solar, backing up a critical load, or enabling more load on a tight connection (see G100 export limitation).
- Your network operator (who is my DNO) and whether solar is already on site, which adds to the G98 or G99 sum.
For installed-cost ranges and what is in them, read the cost guide; for grid connection, the G99 application guide.
Pre-check FAQs
What does this pre-check do?
It does three sums and nothing else: how long a battery lasts at full power (energy divided by power), the minimum energy needed to cover a peak of a given size and length (power times hours), and whether the combined power is above the 16 A per phase line that separates G98 from G99. It shows no prices, savings or payback, because those depend on your meter data and tariff.
Why does it not show savings or payback?
Because they cannot be calculated honestly without twelve months of half-hourly meter data, your actual tariff and charges, and a design. Any number produced from a postcode or a spend figure would be a guess. Give each installer your half-hourly data and ask for the savings case itemised, with its assumptions shown.
Is the answer the size of battery I need?
No. Real systems need margin for conversion losses, usable versus nameplate capacity, degradation and the control strategy. The pre-check gives the arithmetic floor so you can sense-check a proposal; the design belongs to a qualified engineer working from your data.
How do I know whether my battery is G98 or G99?
The line in the ENA guide is 16 A per phase for the combined generation and storage at the premises; above it, a Type A system is G99 and needs the network operator's agreement before installation. The G99 application guide on this site has the full checker and the stages.