Commercial Battery Storage Installation, Engineered and Commissioned
UK commercial battery installers. We survey, apply for G99, engineer the connection and fire siting, install containerised or indoor, and hand over a witnessed commissioning pack.
- MCS Certified
- NICEIC
- G99 / G100
- PAS 63100
- CDM 2015

A commercial battery install is a grid-connection project
Installing a commercial battery energy storage system (BESS) is an engineering and grid-connection project, not a product purchase. The payback maths is the easy part; the programme is set by the DNO. A behind-the-meter commercial battery needs a G99 connection agreement (or a G100 export/import limitation scheme where the network is constrained), half-hourly metering, protection and switchgear that integrate cleanly into the existing supply, a fire risk assessment and siting design that satisfies the insurer and the fire authority, and a witnessed commissioning and O&M handover. Get the sequence wrong and the DNO study alone can add six to eighteen months. This site is built by installers, not brokers: we lead on how a commercial BESS is actually delivered, from feasibility survey and half-hourly data pull, through G99 submission and DNO liaison, containerised or indoor cabinet siting to PAS 63100 and BS EN 62619 fire-safety standards, protection and G100 limitation design, to witness testing, commissioning, and a documented O&M regime. The economics matter, but a correctly engineered and connected install is what actually delivers them.
- We submit the G99 application at survey and show the DNO milestone honestly as the critical path, no programme surprises.
- Fire siting to PAS 63100 / BS EN 62619 / BS EN 62933 with the insurer and fire authority engaged before we install, not after.
- One accountable contractor across survey, G99/G100 design, civils, install, protection, and witnessed commissioning.
- G100 export/import limitation engineered in so you can install on a constrained connection without a costly reinforcement.

The install runs on three gates: connection, fire, commissioning
From feasibility survey to witnessed commissioning
One accountable contractor across survey, G99/G100 design, fire siting, civils, install, protection and testing.
- 01Week 1-2
Feasibility survey & HH data
We pull 12 months of half-hourly data, confirm your supply capacity and available fault level, and settle the siting and fire strategy before any plant is ordered.
- 02Month 1 onward
G99 application & DNO liaison
We submit the G99 application, single-line diagrams and protection proposals on day one, and engineer a G100 limitation scheme where the network is constrained.
- 03Month 1-3
Fire siting & design freeze
Separation distances, detection, ventilation and firefighting access designed to PAS 63100 and NFCC guidance, with your insurer and fire authority engaged up front.
- 04Install 1-6 weeks
Install, tie-in & witnessed commissioning
Container craned or cabinet installed, protection and metering integrated into your switchgear, then a documented, witnessed commissioning and O&M handover.
Every way we install commercial storage
Containerised or indoor, retrofit or standalone, resilience or EV-buffer. Each is sized and sited differently. Pick yours.

Containerised Outdoor BESS Installation
250 kW / 500 kWh-2 MW / 4 MWh. £180,000-£2.4m. 7-year payback.

Indoor Cabinet BESS Installation
30 kW / 60 kWh-250 kW / 500 kWh. £45,000-£300,000. 7.5-year payback.

Solar-Plus-Storage Retrofit
50 kW / 100 kWh-500 kW / 1 MWh. £60,000-£650,000. 6.5-year payback.

Standalone Grid-Services Install
1 MW / 2 MWh-20 MW / 40+ MWh. £800,000-£20m+. 8-year payback.

Backup & Resilience Install (Islanding)
50 kW / 100 kWh-1 MW / 2 MWh. £80,000-£1.5m. 8-year payback.

EV Charging Hub Storage Install
100 kW / 200 kWh-1 MW / 2 MWh. £120,000-£1.4m. 7-year payback.

500 kW / 1 MWh containerised BESS installed at a Midlands manufacturer
A precision manufacturer needed to add production load but the DNO quoted a long reinforcement for extra import capacity. Existing 400 kW rooftop solar exported surplus at midday. The site had yard space but no spare plant room. The install challenge was siting a container safely, tying into live HV switchgear without stopping production, and connecting on a constrained network.
The commercial case, honestly
An installed battery is an owned asset, not a rented cost
A correctly engineered install is what turns the business case into cash. A behind-the-meter battery is plant on your balance sheet: qualifying spend attracts 100% Annual Investment Allowance on the first £1m and a 50% first-year allowance on the balance (storage is special-rate — not full expensing). A 250 kW / 500 kWh system typically installs for £150,000-£300,000; a 1 MW / 2 MWh system for £600,000-£1.2m, with a 6-8 year payback once the demand-charge, self-consumption and resilience value is engineered in.
Self-consumption, not spill
Retrofitting storage to existing solar lifts self-consumption from 40-60% toward 80%+ and time-shifts export into higher-priced Smart Export Guarantee (SEG) windows instead of spilling surplus at midday.
Why start the G99 now
The DNO connection queue is the programme. Every month you delay the G99 application is a month added to go-live. Constrained networks are getting busier, so the earlier we apply, the sooner you connect.
What you're covered by
An itemised, fixed-price proposal, a 10-year insurance-backed workmanship warranty, a documented commissioning pack, and a planned O&M regime. No-obligation feasibility, and we will tell you honestly if your profile does not justify a battery.
Specialist BESS installer vs a general electrical contractor
| Specialist installer (us) MCS, G99/G100, PAS 63100 | General electrical contractor Broad remit, not BESS-focused | Battery supplier only Sells the kit, not the install | |
|---|---|---|---|
| Prepares & submits the G99 application | Sometimes | ||
| Engineers a G100 limitation scheme | |||
| PAS 63100 fire siting & FRA | |||
| Integrates protection into live switchgear | Sometimes | ||
| Half-hourly metering / CT design | |||
| CDM 2015 principal contractor | Sometimes | ||
| Witnessed commissioning & O&M pack |
Where we install
Commercial battery storage installation across the UK. Each area page carries the local DNO, grid-connection context, industrial estates and council net-zero target.

London
Greater London. 8,908,081 population. Greater London Authority.

Birmingham
West Midlands. 1,141,816 population. Birmingham City Council.

Leeds
West Yorkshire. 793,139 population. Leeds City Council.

Sheffield
South Yorkshire. 584,853 population. Sheffield City Council.

Manchester
Greater Manchester. 568,996 population. Manchester City Council.

Bradford
West Yorkshire. 546,412 population. Bradford Council.
Installation questions we hear most
Straight answers on timelines, G99, fire safety and commissioning — the things that actually decide a BESS project.
How long does a commercial battery storage installation take?
Physical installation is typically 1-6 weeks on site for a behind-the-meter system. The overall programme, however, is set by the DNO: a G99 study and connection can run 3-18 months depending on network capacity in your area. We submit the G99 application alongside the survey so the clock starts immediately, and use a G100 limitation scheme where it lets the project proceed sooner. Grid-scale standalone projects run 18 months to several years including planning.
What is the G99 process and why does it drive the timeline?
G99 is the Energy Networks Association connection agreement required for storage above 16 A per phase, which covers almost every commercial system. The DNO reviews the connection, may require a network study, and sets the protection and metering requirements. Because network capacity is limited in many areas, the study and connection offer are usually the longest item on the programme. We prepare the application, single-line diagrams, and protection proposals, liaise with the DNO, and, where the network is constrained, engineer a G100 export/import limitation scheme so the site can connect within its existing agreed capacity.
Containerised outdoor BESS or an indoor cabinet, which suits my site?
It comes down to space, capacity, and fire strategy. A containerised outdoor system is usually the fastest route to multi-MWh capacity and keeps the fire and space constraints outside the building, but it needs prepared hardstanding, separation distances, and firefighting access. An indoor cabinet suits smaller systems (roughly 60-500 kWh) at sites with a suitable plant room or switchroom, but the room must be compartmented, ventilated, and fire-detected. We assess both against your available space, target capacity, and insurer requirements at the survey.
What fire safety standards apply to a commercial battery installation?
We design to PAS 63100:2024 principles for installation and fire protection, BS EN 62619 for cell safety, and BS EN/IEC 62933 for system safety, with NFCC guidance for larger and grid-scale sites. We specify lithium-iron-phosphate (LFP) cells for their thermal stability, and engineer separation distances, detection, thermal monitoring, and appropriate compartmentation or bunding. A fire risk assessment is produced and the insurer, and where necessary the fire authority, engaged before installation.
Do you handle the DNO application and grid connection, or do we?
We handle it as part of our scope: the G99 application, single-line diagrams, protection settings, half-hourly metering arrangement, DNO liaison, and witness-test coordination, plus the G100 limitation design where the network is constrained. You get one accountable contractor across survey, design, connection, install, and commissioning rather than having to coordinate a battery supplier, an electrician, and the DNO yourself.
Can you install a battery without shutting down our operations?
In most cases yes. The tie-in to your existing switchgear is planned around your operations using temporary supplies, out-of-hours working, or a short pre-agreed outage only where unavoidable. We establish your supply arrangement, available fault level, and switchroom access at survey so the connection method is designed, method-statemented, and risk-assessed before we mobilise. Minimising disruption is a design-stage decision, not an on-the-day improvisation.